Construction photos: week 3 (footings)

In construction photos by Michael Tiemann

With everything looking good, Week 3 started to show real progress. In the first half of the week, trenches for the footings were dug. Here is the amazing backhoe that did that work:
Backhoe
Why do I say “amazing”? Because the hydraulic backhoe was a revolutionary piece of machinery that made it economical to do constructions such as this one. As Clayton Christensen explains in his book The Innovator’s Dilemma the hydraulic backhoe was a product without a market when it was introduced in the 1940s. Cable-actuated steam shovels moved many cubic yards of earth with each scoop, whereas the first hydraulic backhoes could move only 1/4 cu yd of earth. When it came to digging the foundations of houses, or better yet, major buildings, or whole mountaintops, steam shovels were king. But when it came to digging trenches, their jaw were too wide to do the job. The lowly hydraulic backhoe was just the thing for digging trenches—much easier than doing it by hand. And today, that innovative technology is proving its value to this project.

In a matter of a few days, all these trenches were dug, rebar positioned, and finished floor elevations outlined using framing lumber. Wes and I looked at these from all angles and decided that yes, the plan and the ground were in agreement, and that the proposed finished floor elevations were perfect as framed. Here are some of the angles we looked at:

Lilypond view of finished floor elevation South southeast finished floor elevation South southeast finished floor elevation (alt)  West finished floor elevations South finished floor elevation

And because I’ve never seen the process before, I took some interest in how the actual trenches were laid and made:

East trenches Northeast trenches Southeast trench detail South Music Room trench South Music Room trench detail Southwest trenches Loggia trench details Control Room trench detail

The morning after signing off on the proposed finished floor elevations, the project received its first inspection, and by noon, the concrete was flowing. I was not there to see it poured, but a day and a half later, the footings had all been poured:

East footings Footings of booths A, B, and C Booth footings (from Booth A) Control Room footings Loggia footings, detail Music Room footings, western end Music Room footings, eastern end Northeast corner footings — Booths B and C North view of footings Southeast corner footings, detail Garage footings, from south Footings and rebar detail Footings and rebar, wide West view of footings Garage footings, from south Southeast view of footings, including garage

The footings are now curing, and we are hard at work on the wiring plan before pouring the foundation. But that’s a blog post for another day!