Weather has been quite a challenge lately, and both snow and rain slowed down our efforts to complete the Annex roof. Nevertheless, there were enough good days to at least enter the final stretch of the roof framing process: sheathing the roof. Here’s the half that we sheathed by the …
Week 111 (Annex Roof Framing)
This week we crowned 14 courses of masonry with the framing of a roof: That’s pretty exciting, considering that last week we had nothing up top, and three months ago the Annex was just some footings and a foundation. Read on to see some of the details of our progress, …
Week 110 (Booth Walls Framed)
Well that was fast…one week we’re laying down the first of our wall plates, and the next, we’re done! With the booth framing, that is. But there’s a lot more happening elsewhere, too…
Authenticity without Originality?
A new article in the New York Times poses a question by way of a quotation: can there be authenticity without originality?
Week 109 (Interior Framing Begins)
If we had decided to build Manifold Recording inside the shell of a commercial building, then we would have started the project at the point we have just now reached: the initial framing of the interior walls. But since we are following the principles of Organic Architecture, we had to …
Filling a Real Need
The artcile Is There an Ecological Unconscious? in the January 31 2010 Sunday New York Times Magazine probes a deep psychological question, examining solastalgia and soliphilia along the way. Both are rooted in the Latin solacium (comfort), but one riffs on nostalgia (which connects to the Greek root –algia (pain …
Colin Broad makes me happy
It was over a year ago when Ben Loftis told me “I think you’re going to need a box from Colin Broad”. I vaguely remember looking up the name, seeing the boxes, and thinking “OK…when I’m a little closer to building out the studio I’ll have to see what’s current …
Week 108 (Lower Roof Shingling and Booth Windows)
This week there was a lot of visible progress, both inside and out. On Monday morning the roofing crew arrived, and on this truck you can see some of the very special equipment and materials that will be used to finish up the lower roof (and later the upper roof, …
Week 107 (Upper Soffit Lamps)
The installation and illumination of lights in the upper exterior soffit has created a dramatic change to the look of the studio, even in daylight. The lights, and the mirror-like finish of the final coat of varnish, merely stoke my anticipation all the more:
Week 106 (Control Room dried in)
This week the framing crew put some skin on the Control Room roof rafters, and we’re now technically dried in! But that’s not nearly all that’s happened, and of course the journey of how we got here is interesting in its own right.
